Laúca / Malanje - The Laúca Hydroelectric Power Plant will reach, by October this year, its maximum capacity of 2,070 megawatts of production, with the entry into operation of the sixth production unit (334 MW) and the ecological plant (66.5 MW).

Send by email

To share this news by email, fill out the information below and click Send

Correct

To report errors in the texts of articles published, fill out the information below and click Send

1 / 1

Elias Estêvão, director de Laúca

Photo: Agostinho Kilemba

Laúca Dam

Photo: Agostinho Kilemba


Currently, there are five turbines in operation with 334 megawatts each, making a total of 1,670 megawatts, consumed by the provinces of Malanje, Cuanza Norte, Cuanza Sul, Zaire, Uíge, Bengo, Luanda, Benguela, Huambo, Bié and very soon the interconnections of the provinces of Huila and Namibe.

The information was released  last Thursday to ANGOP, by the general director of the Laúca Hydroelectric Development, Elias Estêvão, on the sidelines of the 10th Consultative Council of the Ministry of Energy and Waters, which is taking place in the referred hydroelectric enterprise, currently the largest in the country.

According to the source, at this point the civil works for the sixth turbine are being concluded, which will be followed by tests for their start-up.

Elias Estêvão said that the project, to be concluded in December this year, will increase the availability of power and consequently increase the number of consumers at the country level.

Read also
  • 06/03/2020 11:47:52

    Six laboratories for water quality control under planning

    Laúca - The minister of Energy and Water, João Baptista Borges, has said that the priority for the water subsector will be the construction of six laboratories in the provinces of Lunda Norte, Malanje, Bié, Namibe and Cabinda for the product quality control.

  • 22/02/2020 12:18:18

    Cacuso gains white potato processing plant

    Malanje - A factory that processes white potatoes into potato chips, called "Palanca", with the capacity to produce 12,000 (40 and 80 grams) packs of this product in six hours, opened on Friday in the Municipality of Cacuso, north-central Malanje Province.

  • 23/01/2020 20:19:17

    Ministry wants more investments in national products

    Malanje - The Secretary of State for Commerce, Amadeu Nunes, today asked the heads of the large commercial establishments in Malanje, to invest more in national products, in order to make a greater contribution to the country's development.